MIRA’s home-building timeline, explained.
Building a new home is an exciting milestone, but understanding what happens between your first conversation with a builder and receiving your keys can sometimes feel overwhelming.
At MIRA Residential, we believe the building process should be just as considered as the home itself.
From your initial consultation and design selections through to off-site manufacturing, transportation and installation, every stage is carefully coordinated by our experienced team.
So, what does the process of building a modular home in Western Australia actually look like?
Let’s take you through it.
Stage 1: Pre-Construction | Approximately 4–6 Months
Before your home enters construction, there’s important groundwork to complete.
The pre-construction phase is where your design, engineering, documentation, approvals and selections come together, ensuring your home is ready for manufacturing.
Initial Consultation and Design
Your journey begins with a conversation.
Our team takes the time to understand your lifestyle, budget, preferred design and building timeframe. We’ll also review your block to assess its suitability for modular construction.
Whether you’re choosing from our existing range of architecturally inspired designs or exploring customisation, we’ll work with you to establish a home that suits your requirements.
Preliminary Works and Site Investigations
Once your design and initial pricing have progressed, you’ll enter into a Preliminary Works Agreement (PWA).
This allows our team to coordinate essential site investigations, which may include:
- Site surveys and classification
- Bushfire Attack Level (BAL) assessments, where required
- Structural engineering
- Energy assessments
- Detailed working drawings
- Certification documentation
These investigations help establish the technical requirements of your home and prepare the project for the next stages.
Building Contract and Prestart
With the necessary documentation prepared, you’ll progress to your HIA building contract, which confirms your agreed scope, inclusions and price.
You’ll then attend your Prestart appointment, either in person or virtually, to finalise your interior and exterior selections.
From cabinetry and flooring to colours, finishes and fixtures, this is where the details of your new home come together.
Our team prepares your final plans and documentation for review and sign-off before progressing to construction.
Building Approvals and Procurement
With your contract and certifications in place, MIRA coordinates the building permit application on your behalf.
Meanwhile, our team prepares detailed fabrication drawings and coordinates the procurement of materials and trades required for your build.
Once the necessary approvals, documentation, selections and procurement are finalised, your home is ready to enter manufacturing.
Stage 2: Off-Site Construction | Approximately 12–14 Weeks
This is where your new home begins to take shape.
Unlike traditional construction, where most building activities take place on your property, MIRA homes are manufactured within our controlled off-site facility in Henderson, Western Australia.
Our manufacturing process brings together precision engineering, skilled trades and rigorous quality control to deliver a high-quality finished product.
Structural Foundations and Steel Framing
Depending on your home’s design, construction begins with either a pre-stressed concrete slab or a steel frame chassis.
Our team then manufactures and assembles the steel wall and roof frames, establishing the structural framework of your home.
Steel framing offers strength, dimensional accuracy and durability, making it particularly well suited to modular construction.
Roofing, Cladding and Windows
With the structural frame complete, your home begins to take on its architectural character.
Roofing and external cladding are installed, followed by windows and external doors to help create a weather-tight structure.
This is often one of the most exciting stages, as your home’s exterior design becomes recognisable.
Interior Construction and Finishes
As construction progresses, attention turns to the interior.
Our trades install wall and ceiling linings, followed by painting, cabinetry, tiling and flooring.
Plumbing and electrical fixtures are fitted, along with the final details that bring your home together, including shower screens, mirrors and robe doors.
Throughout manufacturing, our team undertakes quality checks to ensure works meet the relevant specifications and standards.
Quality Inspections and Preparation for Transport
Before your home leaves our Perth-based facilities, it undergoes comprehensive quality assurance inspections and commissioning activities.
Practical Completion inspections are conducted with the client, and identified defects are addressed before handover.
For multi-module homes, the completed structure is carefully separated into individual modules and prepared for transportation using hydraulic jacking systems.
Your home is now ready to make its journey to your property.
Stage 3: Transport, Installation and Handover | Approximately 1–4 Weeks
One of the most distinctive parts of modular construction is seeing a completed home arrive at its final destination.
At MIRA, we operate our own dedicated transport fleet, allowing us to coordinate deliveries throughout metropolitan, regional and remote Western Australia.
Transporting Your Home
Transporting a modular home requires careful planning.
Our team coordinates the necessary transport arrangements, including delivery logistics and installation requirements, to help ensure each module reaches its destination safely.
Managing transport in-house also allows us to coordinate manufacturing, delivery and site installation as part of the broader construction programme.
Installation and Complexing
Once your home arrives, the modules are carefully offloaded and positioned onto their prepared foundations.
Depending on site requirements, installation may involve hydraulic jacking systems or crane lifting.
For multi-module homes, the individual sections are aligned, structurally connected and complexed to create the finished home.
Our team then completes the required service connections and commissioning, including water, sewer, power and communications.
Any remaining site-related works are coordinated and completed in accordance with the project’s scope.
Practical Completion and Key Handover
With construction, installation and final works complete, it’s time for one of the most anticipated moments of the journey: receiving your keys.
At handover, you’ll receive the relevant documentation, warranties, operating manuals and maintenance information for your new home.
MIRA also provides a six-month maintenance period, during which defects are managed in accordance with your building contract.
It’s all part of our commitment to supporting clients beyond construction.
Stay Connected Throughout Your Build
We understand how important it is to know what’s happening with your home, particularly when much of the construction takes place away from your property.
That’s why MIRA clients receive access to our dedicated online Client Portal.
Throughout your journey, you’ll benefit from:
- A dedicated Client Experience Consultant
- Step-by-step project updates
- Visibility of key construction milestones
- Access to important project documentation
- Clear communication throughout the building process
Whether your home is progressing through approvals, manufacturing or installation, our team is there to guide you through each stage.
How Long Does It Take to Build a Modular Home in WA?
The total timeframe for building a modular home involves more than the manufacturing period alone.
At MIRA Residential, our indicative project stages are:
| Building stage | Indicative timeframe |
|---|---|
| Pre-construction, design and approvals | 4–6 months |
| Off-site manufacturing | 12–14 weeks |
| Transport, installation and on-site works | 1–4 weeks |
These timeframes are indicative and may vary depending on project complexity, design requirements, selections, approvals, site conditions, weather and other factors.
One of the key advantages of modular construction is that certain site preparation activities can take place while your home is being manufactured, helping streamline the overall construction programme.
A Better Building Experience Starts with a Considered Process
At MIRA Residential, building a home is about more than the finished product.
It’s about combining thoughtful design, precision manufacturing, experienced project management and clear communication to deliver a high-quality home and a positive building experience.
From your first consultation to the moment you receive your keys, our team is committed to guiding you through every stage.
Ready to start your home-building journey?
Explore our range of architecturally inspired modular homes or speak with our friendly team about bringing your new home to life.